If your Electrical Installation Condition Report (EICR) comes back “unsatisfactory”, a legal clock starts running. Under the 28-Day EICR Rule, England’s private landlords must act within a fixed window or risk enforcement action and a significant financial penalty. This guide explains the deadlines, what counts as “completed”, and how to stay compliant without last-minute panic.
What Is the 28-Day EICR Rule?
The rule comes from the Electrical Safety Standards in the Private Rented Sector (England) Regulations 2020. It applies to private rented homes in England, and the regime has since been extended to social rented housing.
When an EICR identifies that remedial work or further investigation is required, the landlord must make sure a qualified and competent person carries it out within 28 days of the inspection, or sooner if the report specifies a shorter period. The 28 days is a maximum. If your electrician says something must be done within 7 days, that shorter deadline is the one that counts.
Your Statutory Deadlines at a Glance
| Obligation | Deadline |
| Give the EICR to existing tenants | Within 28 days of the inspection |
| Give the EICR to new tenants | Before they occupy the property |
| Give the EICR to a prospective tenant who asks | Within 28 days of the request |
| Give the EICR to the local authority on request | Within 7 days of the request |
| Complete remedial or further investigative work | Within 28 days, or sooner if the report says so |
| Send written confirmation of completed work to tenants and the local authority | Within 28 days of completion |
These are two separate clocks. The first covers getting the work done. The second covers proving it. Many landlords fix the problem on time and still breach the regulations because they never send the written confirmation.
Understanding EICR Codes and What They Mean for Your Deadline
Your electrician will classify each observation with a code:
- C1 (danger present): There is an immediate risk to safety. A responsible electrician will normally make the circuit safe on the day, and the fix should not wait for the 28th day.
- C2 (potentially dangerous): Not an immediate hazard. But it could become one. This falls squarely within the 28-day rule.
- FI (further investigation required): The inspector could not fully assess something. The further investigation must also be completed within 28 days, or sooner if the report specifies.
- C3 (improvement recommended): Good practice, but not a mandatory trigger for the 28-day rule.
Any report with a C1, C2 or FI code is classed as unsatisfactory, and the deadline applies.
When Does the 28-Day Clock Actually Start?
The 28 days is measured from the date of the inspection stated in the report, not from the day the report lands in your inbox. If the inspection took place on 1 March but the report was issued on 8 March, you have already used a week.
For that reason, book your EICR with enough lead time. Do not schedule it for the week before a tenant moves in or before you plan to serve notice.
What Counts as “Completed” Remedial Work?
Having the work done is not enough. You need written confirmation from a qualified person that the remedial or further investigative work has been carried out and that the electrical safety standards are now met (or that further work is still required).
Acceptable evidence typically includes:
- A new satisfactory EICR, if the original was substantially reinspected
- An Electrical Installation Certificate (EIC) for new circuits or a consumer unit replacement
- A Minor Electrical Installation Works Certificate for smaller repairs
Once you hold this confirmation, send a copy to each tenant and the local housing authority within 28 days of completion. Keep proof of when and how you sent it.
Who Is Allowed to Carry Out the Work?
The regulations require a “qualified person”, meaning someone competent to inspect, test and certify the work. In practice, use an electrician who is registered with a recognised competent person scheme, such as NICEIC, NAPIT or ELECSA. They should work to the current edition of the IET Wiring Regulations (BS 7671).
Be cautious about using a different contractor for the repair than the one who carried out the inspection. That is allowed, but make sure the certification you receive is complete enough to satisfy the council.
What Happens If You Miss the Deadline?
If you do not complete the works in time, or you fail to provide the required confirmation, your local housing authority can step in. Its powers include:
- Serving a remedial notice requiring you to take action
- Carrying out the work itself, with tenant consent, and recovering the cost from you
- Issuing a civil financial penalty of up to £30,000 per breach
You can appeal a penalty to the First-tier Tribunal, but the appeal window is also short, at 28 days. Councils across England have been actively enforcing these regulations, so treat the deadline as a hard legal limit rather than a guideline.
There is also a practical consequence. Failing to provide a valid EICR can undermine your ability to regain possession of a property, because compliance with landlord safety duties increasingly affects your legal position when ending a tenancy.
Can You Ever Get More Time?
The regulations include a limited defence. You will not be in breach if you can show that you took all reasonable steps to comply. For example, you may have repeatedly tried to arrange access, and your tenant refused or failed to cooperate.
Evidence is everything here. Keep dated emails, texts, letters and call notes. A vague claim that the tenant “was difficult” will not satisfy a council or tribunal. A documented paper trail of repeated, reasonable attempts might.
If the delay was caused by the electrician’s availability or parts supply, that is generally not a defence on its own. Get quotes and book the work as soon as you receive the report.
A Practical 28-Day Timeline for Landlords
| Day | Action |
| Day 0 | EICR inspection completed |
| Day 1–3 | Receive report, review codes, circulate to tenants |
| Day 3–7 | Obtain quotes and book the remedial works |
| Day 7–21 | Electrician completes remedial work and issues certification |
| Day 21–28 | Send the written confirmation to tenants and the local authority |
Aim to finish early. A buffer of a few days covers failed appointments, material delays and last-minute re-testing.
Common Mistakes That Cause Landlords to Breach the Rule
- Counting from the wrong date. The clock starts at inspection, not report delivery.
- Doing the work but skipping the paperwork. Without written confirmation, you are still non-compliant.
- Forgetting the council. The completion confirmation must go to the local authority as well as the tenant.
- Ignoring FI codes. Further investigation is not optional.
- Waiting until the end of the window. One cancelled visit can push you past the legal limit.
Is the Rule the Same Across the UK?
No. This article covers England. Wales, Scotland and Northern Ireland each have their own electrical safety requirements and timeframes. If you own properties across the UK, check the rules for each jurisdiction rather than assuming the English deadlines apply.
How London Property Inspections Can Help
At London Property Inspections, we help landlords, letting agents and property managers across London stay on the right side of the regulations. Our qualified electricians carry out thorough EICR inspections and provide clear, plain-English reports. We can also coordinate the remedial works and issue the certification you need, so you are not left chasing multiple contractors against a ticking clock.
If your EICR has come back unsatisfactory, contact us as early as possible. The sooner we begin, the more room you have to complete the works, document them and notify everyone within the statutory timeframe.
FAQs
What is the 28-Day EICR Rule?
The 28-Day EICR Rule requires landlords in England to complete any remedial or further investigative work identified in an unsatisfactory EICR within 28 days of the inspection, or sooner if the report states a shorter period. You must then provide written confirmation of completion to your tenants and local authority within 28 days.
When does the 28-day period begin?
It begins on the date of the inspection shown on the report. Not the date you receive it. This is why acting quickly after the inspection is so important.
What if my tenant won’t let the electrician in?
You may be able to show you took “all reasonable steps” to comply, but only if you can evidence repeated, documented attempts to arrange access. Keep copies of every message and letter, and contact your local authority if you cannot resolve the problem.
Do C3 observations have to be fixed within 28 days?
No. C3 means “improvement recommended” and does not trigger the mandatory 28-day requirement. You should still consider addressing these items as good practice, but only C1, C2 and FI codes make a report unsatisfactory.
What is the penalty for missing the 28-day deadline?
Your local housing authority can issue a financial penalty of up to £30,000 per breach, and may also serve a remedial notice or arrange the work itself with tenant consent. You can appeal a penalty to the First-tier Tribunal, but you need to act within 28 days of the penalty notice.